FK Engineering ( Provide complete Industrial Solution ) , a trusted name in the industrial and infrastructure development sector, proudly announces the successful completion of Phase 1 of the Babu Jee Flour Mill (BFM) project. This milestone includes the full completion of civil, mechanical, and electrical works for the ground floor, laying a strong foundation for the upcoming operational capacities of the plant.
Scope of Work Completed in Phase 1
The first phase was a combination of multi-disciplinary expertise and flawless execution. FK Engineering’s dedicated project team worked relentlessly to ensure quality, efficiency, and safety throughout the execution of the following works:
Civil Work at BFM on the Ground Floor
The ground floor construction was completed with high precision, using premium-grade RCC and modern formwork techniques. Key features of the civil work include:
- Industrial-grade reinforced concrete foundations for heavy milling machinery.
- Anti-vibration flooring for smooth machinery operation.
- Room partitions for raw material storage, control rooms, and electrical enclosures.
FK Engineering handled all mechanical installations for Phase 1, which involved:
- Fabrication and mounting of machinery foundations for roller mills and sifters.
- Assembly of material handling equipment including elevators, conveyors, and feed chutes.
- Structural support systems for future vertical expansions.
Electrical Setup
An efficient Complete Electrical Services was crucial for power distribution, safety, and automation readiness. FK Engineering delivered:
- Laying of electrical conduits and cable trays.
- Installation of main distribution boards (MDBs) and sub-panels.
- Earthing, lighting, and control panel rooms.
Phase 2 Underway: Second Floor Civil Work in Progress
With the ground floor phase completed, FK Engineering has now entered Phase 2 of the project. This includes the ongoing civil construction of the second floor, which will support the next level of mechanical and processing units.
Key highlights of Phase 2 include:
- Column extensions and formwork for slab casting.
- Structural integration with the ground floor.
- Preparations for second-floor equipment foundations.
This floor is critical for housing sifters, pneumatic pipes, and automated control systems in the later stages of the project.
Commitment to Quality and Safety
FK Engineering is known for its unwavering commitment to quality, timely delivery, and site safety protocols. During the execution of this project:
- All work was supervised by licensed engineers and project managers.
- The project followed ISO-standard safety practices.
- Continuous quality checks and client-side reporting ensured transparency.
Client Satisfaction – A Testament to Our Work
The management of Babu Jee Flour Mill expressed deep satisfaction with the quality of workmanship and project management offered by FK Engineering. Their feedback reinforces our core philosophy of “Build it Once, Build it Right.”
What’s Next in the BFM Project
Following the second-floor construction, the upcoming phases include:
- Installation of advanced flour milling machinery.
- Full-scale automation and control system integration.
- Silo erection and bulk storage system setup.
Words from FK Engineering Management
“Completing the first phase of Babu Jee Flour Mill is not just a project milestone—it’s a testament to FK Engineering’s capability in managing complex, industrial-scale projects. We’re excited for the next phase and confident in delivering excellence as always.”
About FK Engineering
FK Engineering is a leading civil, mechanical, and electrical contracting company in Pakistan, with a strong portfolio in flour mills, ghee plants, feed mills, and industrial estates. With a team of professional engineers, project managers, and skilled labor, FK Engineering brings efficiency and excellence to every site.